We have been working with the Town and the Community Path Project Committee (CPPC) to refine the preliminary path design to incorporate comments received from abutters, the Town, and the CPPC.
You my have seen our survey crews along the railroad during the last few weeks. They have been gathering additional survey information that is needed to progress the design, such as tree sizes and additional information behind 7 Channing Road.
Our geotechnical engineers received the executed entry license agreement from the MBTA on Wednesday 2/10. They are now working with Keolis to schedule flaggers so they can access the railroad property to conduct the borings required to complete the Alexander Avenue underpass design and the design for new retaining walls along the proposed path alignment.